Development Timeline Updates

Following a comprehensive procurement exercise, Peveril Securities has been selected as the council’s development partner for the Royal Arcade scheme in Crewe town centre.


A development agreement was signed in October 2020 to deliver a leisure-led mixed-use development on the site, phase one of which will include a new bus station and multi-storey car park.

Royal Arcade Development Site Timeline

Milestone

Expected start / end

Started on site

​ April 2022

Demolition of former bus garages

April 2022 – August 2022

Temporary bus station construction

August 2022 – January 2023

​Temporary bus station operational

January 2023 – December 2023

​Demolish existing bus station buildings

​January 2023 – February 2023

Construct new bus station and multi-storey car park

February 2023 – December 2023

​New bus station operational

December 2023

New multi-storey car park operational

December 2023

Bus Station


The new bus station and multi-storey car park will be completed in four stages. The images below give you more information about the works that will take place.

We have committed to keeping an operational bus station on the site throughout all phases of demolition and construction, which is expected to be completed by the end of 2023.


See the updated Bus Station visuals in the document below: